Transforming homes

Timetable for improvements

Transforming Homes started in July 2013 and will run for a period of 6 years.

We are working across the whole of Thurrock during these 6 years. Our contractors page explains when we will be working in your street.

Our area-by-area timetable for remaining internal improvements is as follows.

January to July 2017

  • Aveley and Uplands
  • Chadwell St Mary
  • West Thurrock and South Stifford

April 2017 to March 2018

  • Aveley and Uplands
  • Chadwell St Mary
  • East Tilbury
  • Stanford-le-Hope West
  • Tilbury St Chad's

April 2018 to March 2019

  • Corringham and Fobbing
  • Grays Thurrock
  • Little Thurrock Blackshots
  • Little Thurrock Rectory
  • Orsett
  • Stanford East and Corringham Town
  • Stifford Clays
  • The Homesteads
  • Tilbury Riverside and Thurrock Park

External work

Any external work needed – including the renewal of any single-glazed windows that remain – will take place between April 2019 and March 2021.