Road closures and street works

Restrictions on roadworks (Section 58 notices)

After we carry out substantial works on roads and public footpaths for which we are the responsible highway authority, we can restrict further works for up to 3 years.

We set these restrictions by serving 'Section 58 notices', as permitted by the New Roads and Street Works Act 1991 (NRSWA): Section 58.

'Substantial works' means works for road purposes that comprise a reconstruction, widening, alteration in the level, resurfacing or specialist non-skid surface dressing of part of the highway.

Restrictions can stay in place from 6 months to 3 years after the completion of works, depending on the type of work completed and the reinstatement category of the road, as set out at GOV.UK: How to reinstate a road after doing street works.

Works can only be carried out during a restriction if the works fall within a category of exempt works – listed at the end of this page – or with our consent.

In the tables below, the number in brackets is the Unique Street Reference Number (USRN).

Section 58 restrictions in force

Restrictions in force on roads and footpaths for which we are the highway authority are listed below.

Road (USRN) Work Period of works End of restriction
A126 slip road to Lakeside Central Roundabout, West Thurrock
(40502174)
Carriageway resurfacing from Lakeside Central Roundabout to a point 100m south 17/07/2022 to 18/07/2022 18/07/2024
A13 eastbound between junctions with the A1089 and Orsett Cock Roundabout
(40502005)
Carriageway resurfacing of the eastbound carriageway from a point approximately 300m east of the junction with the A1089 to a point approximately 690m east 29/01/2024 to 02/02/2024 02/02/2026
Abbotts Drive, Stanford-le-Hope
(40500007)
Carriageway resurfacing from the Southend Road Roundabout junction to west of the Monks Haven junction 27/07/2023 to 28/07/2023 28/07/2025
Abbotts Drive, Stanford-le-Hope
(40500007)
Carriageway resurfacing from outside number 141 to the junction with The Sorrells 02/04/2024 to 03/04/2024 03/04/2026
Araglen Avenue, South Ockendon
(40500046)
Footway reconstruction and new full height kerbing along the side where house numbers are odd numbers, from the junction with Arisdale Avenue for approximately 150m 21/08/2023 to 04/09/2023 04/09/2026
Arterial Road, North Stifford
(40500065)
Carriageway resurfacing from the Cuckoo Lane junction for approximately 205m east 03/04/2023 to 07/04/2023 07/04/2025
Arterial Road, West Thurrock
(40500067)
Carriageway resurfacing from the Arterial Road roundabout A1306 junction to a point 217m southwest 20/07/2022 to 23/07/2022 23/07/2024
Arterial Road, West Thurrock
(40500067)
Carriageway resurfacing from approximately 60m southeast of the roundabout junction off A1306 for Lakeside to approximately 125m away 24/10/2022 to 05/11/2022 05/11/2024
Arterial Road, West Thurrock
(40500067)
Carriageway resurfacing on east and westbound carriageways from the roundabout at the junction with West Thurrock Way to a point approximately 104m east 08/08/2023 to 16/08/2023 16/08/2025
Arterial Road Roundabout, West Thurrock
(40501585)
Carriageway resurfacing in hatching and lane 1 for approximately 40m 08/08/2023 to 16/08/2023 16/08/2025
Bedford Road, Grays
(40500113)
Carriageway resurfacing from east of the Stanley Road junction to approximately 70m east 28/11/2022 to 28/11/2022 28/11/2024
Brennan Road, Tilbury
(40500171)
Carriageway resurfacing from the Civic Square Roundabout junction to east of the mini roundabouts at the Feenan Highway and Parkside Avenue junction 21/05/2023 to 21/05/2023 21/05/2025
Brennan Road, Tilbury
(40500171)
Footway reconstruction from outside number 19 to outside number 31 10/04/2023 to 02/06/2023 02/06/2026
Broxburn Drive, South Ockendon
(40500199)
Carriageway resurfacing from the boundary line between numbers 182 and 184 to its junction with Afton Drive 19/02/2024 to 23/02/2024 23/02/2026
Buckingham Hill Road, Linford
(40500206)
Carriageway resurfacing from the East Tilbury Road junction to approximately 35m north 24/05/2022 to 27/05/2022 27/05/2024
Buxton Road, Grays
(40500223)
Footway reconstruction, entire footway on both sides 25/07/2022 to 02/09/2022 02/09/2025
Chadwell Hill, Chadwell St Mary
(40500271)
Carriageway resurfacing from the junction with Chadwell Bypass to a point approximately 270m north 29/05/2022 to 12/06/2022 12/06/2024
Chadwell Hill, Chadwell St Mary
(40500271)
Carriageway resurfacing from the junction with River View and Linford Road to a point approximately 319m south 08/04/2024 to 11/04/2024 11/04/2026
Chadwell Road, Grays
(40500273)
Carriageway resurfacing from the roundabout junction with River View and the B149 Chadwell Bypass to approximately 197m northwest 29/11/2022 to 30/11/2022 30/11/2024
Chadwell Road, Grays
(40500273)
Carriageway resurfacing from the junction with Northfields for approximately 111m northeast 19/02/2024 to 20/02/2024 20/02/2026
Church Hill, Stanford-le-Hope
(40500303)
Carriageway resurfacing from the centre of the junction with King Street to its junction with The Green 25/02/2024 to 25/02/2024 25/02/2026
Claudian Way, Chadwell St Mary
(40500322)
Carriageway resurfacing from the Brentwood Road junction to 10m east of Waterson Road 25/07/2022 to 29/07/2022 29/07/2024
Cliff Place, South Ockendon
(40500324)
Footway reconstruction, entire length of both footways 03/08/2022 to 24/08/2022 24/08/2025
College Avenue, Grays
(40500334)
Carriageway resurfacing from the Bradleigh Avenue junction to the mini roundabout junctions of Southend Road, Chadwell Road and the A1013 24/10/2022 to 27/10/2022 27/10/2024
College Avenue, Grays
(40500334)
Footway reconstruction along the side with even-numbered properties, from Bradleigh Avenue to Langthorne Crescent 02/10/2023 to 03/11/2023 03/11/2026
Coronation Avenue, East Tilbury
(40500358)
Carriageway resurfacing from the junction with Farm Road to junction with Queen Mary Avenue 20/01/2024 to 21/01/2024 21/01/2026
Courtney Road, Chadwell St Mary
(40500362)
Carriageway reconstruction from outside number 28 to outside number 80 27/02/2023 to 28/02/2023 28/02/2026
Crofton Avenue, Corringham
(40500377)
Carriageway and footway reconstruction from the Lyndhurst Road junction to Bellmaine Avenue 15/05/2023 to 26/05/2023 26/05/2026
Daiglen Drive, South Ockendon
(40501525)
Carriageway resurfacing from approximately 23m north of the Erriff Drive junction to approximately 50m south 26/10/2023 to 27/10/2023 27/10/2025
Devonshire Road, Chafford Hundred
(40500427)
Carriageway resurfacing from the telephone exchange to approximately 200m north of Devonshire Close 21/11/2023 to 25/11/2023 25/11/2025
East Thurrock Road, Grays
(40500462)
Carriageway resurfacing from a point approximately 13m west of the junction with John Street to approximately 10m south of Whitehall Lane 04/10/2023 to 04/10/2023 04/10/2025
East Tilbury Road, Linford
(40500463)
Carriageway resurfacing from the Buckingham Hill Road junction to approximately 70m south 24/05/2022 to 27/05/2022 27/05/2024
Fen Lane, Orsett
(40500511)
Carriageway resurfacing from Stifford Clays Road to Green Lane, approximately 625m 30/08/2022 to 01/09/2022 01/09/2024
Fort Road, Tilbury
(40500539)
Carriageway resurfacing from the junction of Gun Hill and Cooper Shaw Road, 90m west 23/05/2022 to 25/05/2022 25/05/2024
Fort Road, Tilbury
(40500539)
Carriageway resurfacing from approximately 12m west of the centre of the entrance to Goldstar to approximately 63m south of the entrance to Tilbury Sewage Works 05/02/2024 to 08/02/2024 08/02/2026
Giffords Cross Road, Corringham
(40500577)
Carriageway resurfacing between its junctions with Chase Road and Laburnum Drive 07/08/2023 to 07/08/2023 07/08/2025
Gloucester Avenue, East Tilbury
(40500583)
Carriageway resurfacing from Princess Margaret Road to outside number 15 20/01/2024 to 21/01/2024 21/01/2026
Gordon Road, Corringham
(40500593)
Carriageway resurfacing from the westernmost junction of Springhouse Road to The Sorrells junction 01/08/2022 to 04/08/2022 04/08/2024
Grangewood Road, Grays
(40500603)
Carriageway reconstruction from outside number 8 to outside number 16 13/02/2023 to 14/02/2023 14/02/2026
Hathaway Road, Grays
(40500648)
Carriageway reconstruction and footway reconstruction on both sides, entire length 29/09/2022 to 18/11/2022 18/11/2025
High Road, North Stifford
(40500675)
Carriageway resurfacing from outside number 8 to the junction with Stifford Interchange Roundabout 12/09/2022 to 13/09/2022 13/09/2024
High Street, Stanford-le-Hope
(40500681)
Carriageway resurfacing from the junction with King Street to the junction with The Green 15/01/2023 to 22/01/2023 22/01/2025
Hoford Road, West Tilbury
(40500694)
Carriageway resurfacing from Muckingford Road to outside Hatchetts, approximately 130m 02/09/2022 to 02/09/2022 02/09/2024
Jefferies Way, Corringham
(40500725)
Footway reconstruction, both sides 30/01/2023 to 24/02/2023 24/02/2026
Lakeside interchange link road off A13 to West Thurrock Way, West Thurrock
(40501991)
Carriageway resurfacing northbound and southbound from approximately 347m north of the Lancaster roundabout junction to approximately 90m north 13/02/2023 to 17/02/2023 17/02/2025
Lampits Hill, Corringham
(40500773)
Carriageway resurfacing from the Southend Road junction to approximately 160m southeast 26/05/2022 to 29/05/2022 29/05/2024
Lance Corporal Nicky Mason Way, Aveley
(40500082)
Carriageway resurfacing from a point approximately 186m northwest of the roundabout at the junction with Belhouse Avenue to a point approximately 105m west 26/02/2024 to 04/03/2024 04/03/2026
Lea Road, Chadwell St Mary
(40500788)
Carriageway reconstruction from outside number 20 to outside number 24 20/03/2023 to 23/03/2023 23/03/2026
London Road, Aveley
(40500823)
Carriageway resurfacing from the junction with Juliet Way for approximately 35m to the junction with New Purfleet Road 13/11/2023 to 15/11/2023 15/11/2025
London Road, Grays
(40500824)
Carriageway resurfacing from Florence Close to Wharf Road 22/10/2023 to 30/10/2023 30/10/2025
London Road, Grays
(40500824)
Carriageway resurfacing of the westbound carriageway from a point approximately 23m east of the junction with Wouldham Road to a point approximately 40m east, and of the eastbound carriageway including the bus lane from the centre of the junction with Askew Farm Lane to a point approximately 16m east 23/03/2024 to 24/03/2024 24/03/2026
London Road, South Stifford
(40500826)
Carriageway resurfacing from the Stoneness Roundabout junction on the eastbound carriageway to approximately 383m east, and on the westbound carriageway to approximately 215m east 22/04/2023 to 25/04/2023 25/04/2025
Love Lane, Aveley
(40500835)
Carriageway resurfacing of carriageway, footway, verge, grass verge on the corner of the Hall Road junction, footway and grass verges from outside number 81 to the Purfleet Road junction 07/11/2022 to 30/06/2023 04/08/2025
Lucas Road, Grays
(40500841)
Footway reconstruction of both footways for their entire length 23/10/2023 to 15/12/2023 15/12/2026
Manor Road, Tilbury
(40500871)
Carriageway resurfacing from the junction with Civic Square to the junction with Christchurch Road 11/09/2023 to 13/09/2023 13/09/2025
Marshfoot Road, Grays
(40500894)
Carriageway resurfacing from a point approximately 255m northeast of the junction with Marshfoot Roundabout to a point approximately 232m south 19/03/2024 to 06/04/2024 06/04/2026
Morant Road, Chadwell St Mary
(40500945)
Carriageway resurfacing outside numbers 32 to 40, and outside number 58 to east of the access road adjacent to number 62 07/11/2022 to 11/11/2022 11/11/2024
Oakway, Stifford Clays
(40500991)
Carriageway reconstruction, entire length 06/02/2023 to 10/02/2023 10/02/2026
Old Dock Approach Road, Grays
(40501849)
Carriageway resurfacing from approximately 265m northeast of the junction with Marshfoot Road to approximately 80m north 03/10/2022 to 06/10/2022 06/10/2024
Oliver Road, West Thurrock
(40501004)
Carriageway resurfacing from approximately 78m west of the entrance for Elliott Hire to approximately 300m east 20/03/2023 to 22/03/2023 22/03/2025
Orsett Road, Grays
(40501013)
Carriageway resurfacing from the Quarry Hill junction to the Titan Road junction 03/07/2022 to 10/07/2022 10/07/2024
Oxford Avenue, Chadwell St Mary
(40501018)
Carriageway reconstruction from outside number 1 to number 7 15/02/2023 to 17/02/2023 07/02/2026
Oxford Avenue, Chadwell St Mary
(40501018)
Footway reconstruction of both footways from a point approximately 35m north of the junction with River View 23/10/2023 to 08/12/2023 08/12/2026
Rectory Road, Grays
(40501120)
Carriageway resurfacing from a point approximately 40m north of the junction with Chadwell Road to a point south of the junction with Chadwell Road for approximately 215m south 19/02/2024 to 22/02/2024 22/02/2026
Poynder Road, Tilbury
(40501080)
Kerbing, footway and carriageway reconstruction from the Raphael Avenue junction to the Gainsborough Avenue junction 06/03/2023 to 17/03/2023 17/03/2026
Public footpath, Langthorne Crescent to College Avenue, Grays
(40502248)
Replacing tarmac, entire length 21/11/2022 to 09/12/2022 09/12/2024
River View, Chadwell St Mary
(40501132)
Carriageway resurfacing from approximately 66m east of the junction with The Haven to the junction with Chelmer Road 24/07/2023 to 26/07/2023 26/07/2025
Ship Lane, Aveley
(40501210)
Carriageway resurfacing from south of the caravan site junction to approximately 60m northwest of M25 junction 31 03/10/2022 to 14/10/2022 14/10/2024
Southend Road, Corringham
(40501242)
Carriageway resurfacing from the Lampits Hill junction to approximately 160m northwest 26/05/2022 to 29/05/2022 29/05/2024
Southend Road, Corringham
(40501242)
Carriageway resurfacing from approximately 484m north of the mini roundabout junction with Lampits Hill to approximately 47m north over the bridge 09/01/2023 to 10/01/2023 10/01/2025
Southend Road, Grays
(40501244)
Carriageway resurfacing from number 12 to the junction of Whitehall Lane 19/06/2022 to 26/06/2022 26/06/2024
Southend Road, Grays
(40501244)
Carriageway resurfacing from the Lodge Lane junction to approximately 50m southwest 14/08/2022 to 15/08/2022 15/08/2024
South Hill, Langdon Hills
(40501229)
Carriageway resurfacing from the junction with Lower Dunton Road to the junction with Tylands Meadow 10/10/2023 to 13/10/2023 13/10/2025
South Road, South Ockendon
(40501231)
Carriageway resurfacing from the mini roundabout at the North Road and West Road junction to south of the Lime Close junction 15/02/2023 to 20/02/2023 20/02/2025
Springhouse Road, Corringham
(40501263)
Carriageway resurfacing from the junction with the exit of St Johns Way to a point approximately 13m northwest of the junction with Giffords Cross Road 22/01/2024 to 25/01/2024 25/01/2026
St Clements Way, West Thurrock
(40502156)
Carriageway resurfacing from the railway bridge to the Oliver Close junction 30/05/2022 to 02/06/2022 02/06/2024
St Michaels Road, Chadwell St Mary
(40501286)
Carriageway and footway reconstruction from number 1 to number 28, with new car park and footway extension 24/10/2022 to 27/01/2023 27/01/2026
Stanford Road, Orsett
(40501307)
Carriageway resurfacing from east of the junction with Sandown Road to a point approximately 501m east 13/05/2024 to 17/05/2024 17/05/2026
Stanford Road, Stanford-le-Hope
(40501308)
Carriageway resurfacing from approximately 50m east of the junction with Saffron Gardens to approximately 190m west 17/07/2023 to 19/07/2023 19/07/2025
Stanford Road, Stanford-le-Hope
(40501308)
Carriageway resurfacing outside new Redrow development site for approximately 120m 14/08/2023 to 17/08/2023 17/08/2025
Stanford Road, Stanford-le-Hope
(40501308)
Carriageway resurfacing from approximately 124m east of the junction with Buckingham Hill Road to a point approximately 225m east 07/05/2024 to 10/05/2024 10/05/2026
The Green, Stanford-le-Hope
(40500612)
Carriageway resurfacing from the Church Hill junction around the cenotaph for approximately 43m 15/01/2022 to 22/01/2023 22/01/2025
The Green, Stanford-le-Hope
(40500612)
Carriageway resurfacing from its junction with Church Hill to the junction with Wharf Road and Corringham Road 25/02/2024 to 25/02/2024 25/02/2026
The Manorway, Stanford-le-Hope
(40500882)
Resurfacing of the eastbound carriageway from a point approximately 23m west of the junction with The Sorrells to a point approximately 59m west 04/03/2024 to 06/03/2024 06/03/2026
Thurloe Walk, Grays
(40501373)
Carriageway resurfacing from the Hathaway Road junction to approximately 45m west 30/05/2022 to 01/06/2022 01/06/2024
Victoria Road, Stanford-le-Hope
(40501409)
Carriageway resurfacing from the centre of the junction with Bell Reeves Close to approximately 50m south of Southend Road roundabout 02/10/2023 to 03/10/2023 03/10/2025
Warren Lane, Grays
(40501422)
Carriageway resurfacing from the junction with Lancaster Road to the junction with Clockhouse Lane 12/02/2024 to 15/02/2024 15/02/2026
West Road, South Ockendon
(40501443)
Carriageway resurfacing from the junction with South Road to approximately 50m past the railway bridge, towards Arisdale Avenue 23/10/2023 to 26/10/2023 26/10/2025
West Thurrock Way, West Thurrock
(40501448)
Carriageway resurfacing of southbound carriageway from the roundabout at the junction with Arterial Road to Lake Rise 08/08/2023 to 16/08/2023 16/08/2025
West Thurrock Way, West Thurrock
(40501448)
Carriageway resurfacing from a point approximately 19m east of the roundabout at the junction with Abberton Way to a point approximately 94m west 11/04/2024 to 13/04/2024 13/04/2026
Whitmore Avenue, Stifford Clays
(40501463)
Footway reconstruction on the side with even-numbered properties 15/01/2024 to 12/04/2024 12/04/2027
Windsor Avenue, Grays
(40501476)
Footway reconstruction from Lodge Lane to The Griffins, even numbers' side only. 03/01/2023 to 27/01/2023 27/01/2026

Section 58 restrictions proposed

Proposed restrictions on roads and footpaths for which we are the highway authority are listed below.

Road (USRN) Work Period of works End of restriction
Afton Drive, South Ockendon
(40500015)
Footway resurfacing from the junction with Cam Green and Avon Green to a point approximately 63m travelling north 22/07/2024 to 09/08/2024 09/08/2026
Arterial Road, West Thurrock
(40500067)
Carriageway resurfacing from east of Arterial Road Roundabout A1306 to a point approximately 1.01km travelling east 24/06/2024 to 27/06/2024 27/06/2026
Claudian Way, Chadwell St Mary
(40500322)
Reconstruction of the southern footway from the junction with Hyder Road to a point approximately 47m travelling west 22/07/2024 to 26/07/2024 26/07/2027
College Avenue, Grays
(40500334)
Footway reconstruction on the even-numbered side from Bradleigh Avenue travelling west to the end of the road 05/08/2024 to 23/08/2024 23/08/2027
Crown Road, Grays
(40500382)
Carriageway resurfacing from the roundabout at the junction with Stanley Road to the junction with Maidstone Road 02/06/2024 to 17/06/2024 17/06/2026
Dennis Road, South Ockendon
(40500417)
Carriageway resurfacing from the junction with with Dennises Lane to a point approximately 1.25km travelling south 19/08/2024 to 22/08/2024 22/08/2026
Dunlop Road, Tilbury
(40500453)
Carriageway resurfacing along the whole road 19/08/2024 to 19/08/2024 19/08/2026
Eastern Way, Grays
(40500467)
Carriageway resurfacing from its junction with Hogg Lane Roundabout to a point approximately 240m southwest 23/05/2024 to 25/05/2024 25/05/2026
Fairway, Stifford Clays
(40500500)
Carriageway resurfacing from the junction with Long Lane to a point approximately 30m travelling north 29/05/2024 to 30/05/2024 30/05/2026
Gordon Road, Corringham
(40500593)
Carriageway reconstruction and resurfacing from number 37 to the junction with Springhouse Road 15/07/2024 to 02/08/2024 02/08/2027
Lodge Lane, Grays
(40500816)
Carriageway resurfacing of the eastbound carriageway from a point approximately 32m east of the junction with the Treacle Mine Roundabout to a point approximately 109m travelling east, and of the westbound carriageway from a point approximately 35m east of the junction with Treacle Mine Roundabout to a point approximately 92m travelling east 12/05/2024 to 20/05/2024 20/05/2026
London Road, Purfleet-on-Thames
(40500825)
Carriageway resurfacing for approximately 35m from the junction with Beacon Hill 05/11/2023 to 05/11/2023 05/11/2025
London Road, Tilbury
(40500828)
Carriageway resurfacing from approximately 39m east of Hume Avenue to the junction with Elizabeth Close 14/08/2024 to 14/08/2024 14/08/2026
London Road, West Thurrock
(40500829)
Carriageway resurfacing from the junction with Stonehouse Corner Roundabout to east of the junction with St Clements Way 27/08/2024 to 30/08/2024 30/08/2026
Long Lane, Stifford Clays
(40500833)
Carriageway resurfacing from a point approximately 57m west of the junction with Connaught Avenue to a point approximately 89m travelling east 29/05/2024 to 30/05/2024 30/05/2026
Lytton Road, Chadwell St Mary
(40500845)
Carriageway resurfacing from the junction with Lever Square to the junction with Templer Avenue 20/08/2024 to 21/08/2024 21/08/2026
Orsett Road, Horndon on the Hill
(40501014)
Carriageway resurfacing from Blackbush Farm entrance to the junction with Gordon Road 05/08/2024 to 06/08/2024 06/08/2026
Princess Margaret Road, East Tilbury
(40501088)
Footway reconstruction from a point approximately 21m southeast of the junction with Love Lane to a point approximately 95m travelling northwest 22/07/2024 to 09/08/2024 09/08/2027
Russell Road, Tilbury
(40501158)
Carriageway resurfacing from the junction with Dock Road to the junction with Dunlop Road 20/08/2024 to 20/08/2024 20/08/2026
Station Road, East Tilbury
(40501314)
Carriageway resurfacing from a point approximately 32m east of the entrance to Readmans Industrial Estate to a point approximately 352m travelling west 15/08/2024 to 16/08/2024 16/08/2026
Stifford Road, Aveley
(40501325)
Reconstruction of the south footway from west of the entrance to Aveley Primary School car park to the junction with Aveley Close 12/08/2024 to 30/08/2024 30/08/2027
Stifford Road, South Ockendon
(40501327)
Reconstruction of the north footway from a point approximately 30m east of the junction with Cander Way to a point approximately 246m travelling east 29/07/2024 to 06/09/2024 06/09/2027
Tank Hill Road, Purfleet-on-Thames
(40501350)
Reconstruction of the south footway from a point approximately 10m west of Tank Lane to a point approximately 126m travelling southwest 29/07/2024 to 16/08/2024 16/08/2027
Turnpike Lane, West Tilbury
(40501387)
Carriageway resurfacing from the junction with Rectory Road for approximately 365m north 12/08/2024 to 13/08/2024 13/08/2027
Weston Avenue, West Thurrock
(40501450)
Carriageway resurfacing from the junction with London Road to a point approximately 380m travelling north 07/08/2024 to 10/08/2024 10/08/2026
Whitmore Avenue, Stifford Clays
(40501463)
Reconstruction of the footway on the odd-numbered side from the junction with Crammavill Street to the junction with Blackshots Lane 12/08/2024 to 08/11/2024 08/11/2027

Other Section 58 notices

National Highways roads and private roads

We are responsible for the maintenance, repair and cleaning of most roads in Thurrock, including footways. We are not responsible for:

  • private roads – these are the responsibility of their residents
  • National Highways roads

You should contact National Highways (formerly 'Highways England') for matters concerning:

  • A13 – from M25 junction 30 to the Tilbury slip road and to the A1089
  • A1089 Dock Approach Road, Tilbury – from the A13 to Asda roundabout
  • St Andrew's Road, Tilbury – from Asda roundabout to Tilbury Dock gate

For details of Section 58 notices served by National Highways, go to GOV.UK: Register of Section 58 notices served by Highways England.

Exempt works and reduced restrictions

This includes:

If we receive a request for a new customer connection, and it's not possible to carry out the works before the restriction comes into force, the works must not be undertaken for at least 20 working days following the completion of the substantial works.

The period of 20 working days covers Mondays to Fridays – excluding bank holidays in England – and includes the restriction start date plus 19 days.