Building Safety Levy

Building Safety Levy (BSL) process

1. Application stage. Whether you use us, a private approved inspector (RBCA) or the Building Safety Regulator, your application must include how many homes you are building, the planning application details, and whether the scheme is a major development. If this information is not provided, we can reject the application, and we must reject an initial notice. 

 

2. Commencement stage: This covers floor areas, planning permission, any exemptions, and whether the site is previously developed land. It must cover all the works in the application, not just the first phase. Important: Developers will need to provide further information for levy calculation at commencement notice stage. 

 

3. Assessment stage: The Council will issue a Levy Liability Notice (LLC), or a Notice of No Charge (NOC). This usually takes up to 5 weeks(standard) or up to 8 weeks if a spot check is required. 

 

4. Pay the Levy: You can pay at any time after receiving the notice, however, the levy must be paid in full before a completion certificate.

 

5. Completion: A completion certificate will be issued once we receive confirmation that the levy has been paid in full.

 

 If your plans change, you may need to send updated levy details or a levy update notice. The Building Safety Levy (England) Regulations 2025