These questions relate to new homes built by the council.

•           1) In the 2022/23 financial year (1 April 2022 to 31 March 2023) how many new homes of any tenure did the council complete?

•           1) a) Please can you provide a breakdown of those new build completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc).

•           2) If the council has a council-owned housing company, in the 2022/23 financial year (1 April 2022 to 31 March 2023) how many new homes of any tenure did the company complete?

•           2) a) Please can you provide a breakdown of those completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc).

•           3) How many homes does the council expect to build in the next five years (ie, from April 2023-March 2028)

•           4) If the council has a council-owned housing company, how many homes does it expect to build in the next five years (April 2023-March 2028)

I would like you to provide this information in the following format:

An email or an excel spreadsheet

Response: 

These questions relate to new homes built by the council.

•           1) In the 2022/23 financial year (1 April 2022 to 31 March 2023) how many new homes of any tenure did the council complete?  NIL

•           1) a) Please can you provide a breakdown of those new build completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc). N/A

•           2) If the council has a council-owned housing company, in the 2022/23 financial year (1 April 2022 to 31 March 2023) how many new homes of any tenure did the company complete? NIL

•           2) a) Please can you provide a breakdown of those completions, by tenure (for example, how many were social rent, shared ownership, market sale, temporary accommodation, etc). N/A

•           3) How many homes does the council expect to build in the next five years (ie, from April 2023-March 2028) 288

•           4) If the council has a council-owned housing company, how many homes does it expect to build in the next five years (April 2023-March 2028) Undecided as Company subject to review

I would like you to provide this information in the following format:

An email or an excel spreadsheet

You are free to use any information supplied to you for your own use, including non-commercial research purposes. However, any other type of re-use, for example, by publishing the information or issuing copies to the public will require the permission of the copyright owner.

Where the copyright is owned by Thurrock Council, you must apply to the Council to re-use the information. Please email information.matters@thurrock.gov.uk if you wish to re-use the information you have been supplied. For information where the copyright is owned by another person or organisation, you must apply to the copyright owner to obtain their permission.

If you are dissatisfied with the way in which the council have managed your FOI request you can pursue an Internal Review by contacting us using the above email address. An internal review must be submitted within 40 working days of your original reply. Your request will be considered by a senior member of the Information Management Team who will update you with the outcome of the review.

If you remain unhappy following the outcome of your Internal Review you may wish to refer your case to the Information Commissioner’s Office (ICO) and details of this organisation can be found at www.ico.org.uk . Please be advised that the ICO will not consider your case until they have confirmation that you have already been through the Internal Review stage with the council.

Request reference:
FOI 12944